Requirments for pipeline crossing drainage ditches and easements

1. Board approval for each crossing

2. Top of pipe a minimum of six feet below the flow line of the ditch

3. All crossings must be marked

4. Payment of $5,000.00 for each ditch/easement crossing in advance 

5. All crossings must be bored

6. Two days notice must be given before beginning each crossing