Requirments for pipeline crossing drainage ditches and easements
1. Board approval for each crossing
2. Top of pipe a minimum of six feet below the flow line of the ditch
3. All crossings must be marked
4. Payment of $5,000.00 for each ditch/easement crossing in advance
5. All crossings must be bored
6. Two days notice must be given before beginning each crossing